Project details
Client
RCPA
Location
Bellevue
Project Duration
5 months
Project Start
November 2024
Project Finish
April 2025
Description
HydraStorm was engaged by TRACC Civil to deesign and supply an alternative infiltration solution for one of their upcoming projects
With support from our business partners at Frankische, We were ablee to design an up-spec infiltration solution.
Each fitted with two Quadro Control shafts to enable future inspection and maintenance across the lifetime of the tanks.
- 3,334 Rigofill ST-B Cubes
- 760 Rigofill ST-B Sidewalls
- 8 Quadro Control Shafts ST-B
- 3,600m2 Geotextile
Facts & Figures
Total footprint 1,072m2
- Tank 1 – L 24m x W: 9.6m x H: 1.32m – Gross Volume: 304.1 3m3, Net Volume: 291.96m3
- Tank 2 – L: 30,4m x W: 8m x H: 1.32m – Gross Volume: 321.02m3, Net Volume: 308.18m3
- Tank 3 – L 30.4m x W: 8m x H: 1.32m – Gross Volume: 321.02m3, Net Volume: 308.18m3
- Tank 4 – L 29.6m x W: 12m x H: 1.32m – Gross Volume: 468.86m3, Net Volume: 450.11m3
Contact Us
HydraStorm thrives on delivering the right solution for the right application, please contact our sales office for the right solution.