At Hydra Storm Precast we love the challenge of creating solutions for our customers.

Recently we were asked by our client to produce 8 large precast blocks for Boom Gate foundations. These blocks required different sizes and configurations of electrical conduit to be placed in precise locations and were to be cast in 4 sizes with matching pairs.

Due to issues on site all of this was required to be completed within one week to meet site deadlines.

We were given the go ahead for the job on a Tuesday and by Friday had moulds erected, reinforcement made, conduits secured in place and casting completed.

The blocks were collected from our yard the next Monday for a priority delivery to FMG Cloudbreak.

Client:FMG